Before starting work, a risk analysis is conducted. However, at the start of the work, circumstances can differ significantly from the initial analysis. This is precisely why a proper LMRA (Last Minute Risk Analysis) is so crucial. The purpose of an LMRA is to conduct a final analysis just before starting work. What hazards and risks are present?
Typically, a checklist or questionnaire is used for LMRAs. You must then complete this checklist at your workplace. Below is an example of a checklist created by the VVT:
In steps 2 and 3, ask yourself the following questions:
1. Does my work match my assignment?
2. Are there hazards in my work and can I deal with them safely?
3. Are the machines in order and can I use them safely?
4. Are all the tools and accessories in order and can they be used properly and safely?
5. Do I know the correct and safe working method and can I apply it?
6. Do my work environment and working conditions pose any unforeseen risks?